Article of the month

HAM paves ahead, but cracks appear, too

 

In the past three-and-a-half years, the hybrid annuity model (HAM) of road construction has grown substantially, but some warts are now showing up: smaller developers are finding financial closure elusive, and over-aged projects awaiting appointed dates are facing termination risk.

 

CRISIL Research’s analysis of road projects under the National Highways Authority of India (NHAI) reveals HAM has expanded its network since its launch in February 2016. Over fiscals 2017 to 2019, HAM projects accounted for a quarter of the executed road projects and 45-50% of the projects awarded.

First the good news: A deep-dive project-by-project analysis by CRISIL Research reveals that of the 6,670 km HAM projects awarded by the NHAI during fiscals 2016 to 2019, a good 70-75% have achieved financial closure, most of them by large developers with a turnover of over Rs 1,500 crore.

 

Now the concern: Though the foundation has been laid, some cracks have surfaced on the HAM highway. The smaller developers, many of which have changed lanes from engineering, procurement and execution (EPC) projects to HAM for the first time, are struggling to secure funding after bidding aggressively, and banks tightening capital requirements. The upshot has been a deceleration in the pace of financial closures.

 

Besides, delays in receiving the appointed date – or the de facto starting date of a project when the NHAI hands over a contract letter to the developer or concessionaire – have worsened. About 4,130 km of the 6,670 km (60-65%) of HAM projects awarded so far have received appointed dates.

 

The average delay in receipt of appointed date is 5-6 months. Around 2,540 km of the 6,670 km of awarded HAM projects are awaiting the appointed date. And over 60-65% of the 2,540 km runs the risk of termination since the wait has exceeded 18 months.

 

Yet, we expect HAM to account for almost half of the NHAI projects awarded between fiscals 2020 and 2022.